End of August Update

A lot seems to have been done this month – we’ve got a porch, the interior walls and ceiling finished, subflooring and all the upstairs hardwood flooring done, a lot of work in the bathroom and a lot of the final electrical work completed. The next most immediate jobs for September are the building of the floating deck that will provide the floor for the porch, porch roofing, eavestroughs and rainwater collection pipes, plumbing work in the bathroom, WC tiling and then toilet and sink installation, lighting installation and most importantly of all, the completion, testing and balancing of the HRV system. The very last thing will be done by Malcolm Isaacs from CanPHI, who will also be coming down to deal with some outstanding airtightness issues with the Motura sliding door and to conduct a blower-door test. We should be pretty close to being able to move in during early October.