General update end of October 2015

Here’s the current state-of-play as of the end of October 2015, and the schedule until mid-December:

  • Site preparation: done.
  • Site survey and pinning: done.
  • Foundation preparation: done.
  • Plumbing rough-in: done.
  • Septic system: in progress.
  • Foundation: pre-cut insulated forms delivered, should be assembled and concrete poured in the first week of November.
  • Merk Leno CLT Structure: left factory 26th October; scheduled to arrive in port of Montreal 9th November; customs clearance anticpated by 16th November; delivery after that; assembly hopefully by end of that week…
  • Optiwin Windows and Doors: ordered and in production; estimated arrival mid-November.
  • Schneiderholz Wood Fibre Insulation: ordered and in production; estimated arrival end of November.
  • Walltherm wood stove, tank and solar thermal water heating system: to be ordered for arrival beginning of December.
  • Siding and trim: to be ordered; to be installed first two weeks of December.
  • Steel roofing: to be ordered; to be installed before Xmas.

The aim is to have a weatherproof shell by Xmas. Then from the New Year, we will be working on the interior.

 

 

 

 

Advertisements

One thought on “General update end of October 2015

  1. Pingback: End of November 2015 update | Wolfe Island Passive House Project

Leave a Reply

Fill in your details below or click an icon to log in:

WordPress.com Logo

You are commenting using your WordPress.com account. Log Out / Change )

Twitter picture

You are commenting using your Twitter account. Log Out / Change )

Facebook photo

You are commenting using your Facebook account. Log Out / Change )

Google+ photo

You are commenting using your Google+ account. Log Out / Change )

Connecting to %s